On Boiler Shop
Date:2011-10-13 11:21:48    Author:kabb    View:595

SPR High Turbidity Wastewater Purification System

Technical Data 7

On Treating Wastewater from Wet Precipitation for Coal-fired Boiler


Flow: 8 cum/h , Land use size for SPR system: 16m²

·Main pollutants in the wastewater:
Suspended Solids : 600 mg/ ~ 3000 mg/l
pH : 3.0 ~ 5.0
·Total power consumption : 0.15 kwh/cum water
·The total processing time : 30 minutes.
·Reclamation applications: water recycling.

ExampleWastewaterPurified waterElimination rate
SuspendedSolids(mg/l)1890299.8%
pH4.16.8

 
                  AFTER   BEFORE                                                SPR system in boiler shop